Parková čtvrťGrant a proxy
Overview of issues

Problems in our residence

For each topic, we provide relevant supporting documents and correspondence.

Contamination of the retention tank with sewage

A wrongly connected riser led sewage into the rainwater system and the irrigation sprayed it over the greenery where people and children walk. Nozzles and hoses were only flushed, not replaced. It must be demonstrated whether the flushing carried out constitutes a sufficient remedial measure.

Serial condensate drain defect

A bursting pump or hose in the ceiling → soaked walls and ruined ceilings. One unit in summer 2025, at least five more households this year across the buildings. In the event of recurring faults, we require an investigation into the cause and a proposal for preventative measures.

Entrance doors

The fault returned and affects several entrances. When closed in the normal way, the door does not shut properly, which compromises the access control function.

Missing as-built documentation for the building

The developer confirmed in writing it has the documentation and refused to hand it over. It is not among the documents passed to the manager. Without it, repairs cannot be planned nor defects claimed. Keeping it is a legal duty.

High temperatures in communal areas

Corridors measured at 24–27 °C against a design of 15 °C; underfloor heating in flats loses its function. In a written statement, the heat supplier stated that the agreed output did not correspond to the building’s actual requirements.

Cleaning, waste, garden

Cleaning invoices do not match the contract. Containers are invoiced without orders. The garden contract ended 05/2026.

An extraordinary contribution to the repairs fund amounting to 2 million CZK

For the purpose of settling the owners’ association’s current liabilities.

Documented

Statements from the authorities, the developer and the contractors.

Below, we summarise the content of the written submissions on the individual topics.

The public health authority did not assess the tank’s decontamination

The hygiene station confirmed it had no contact with the developer, assessed nothing, measured nothing and issued no opinion. Owners were told it had approved the remediation.

HSHMP 36423/2026 · HSHMP 39210/2026

According to a statement from the authority, no report was drawn up; the matter was referred for consideration as an administrative offence

The environment department confirmed no on-site inspection report exists and is referring the matter as an offence under the Water Act.

UMCP3 417375/2026

Recommended measures were not carried out

The notice of 18 May 2026 recommended an accredited soil analysis and disinfection of the irrigation pipes. Neither happened.

UMCP3 302249/2026

The car park has no meter of its own

The operator confirmed in writing it did not set up its own metering point and the car park’s consumption ran through the association’s meters, contrary to the explicit contract wording.

Written statement, forwarded by the manager

The developer holds the documentation and will not release it

The developer’s written statement confirms it holds the as-built documentation and refuses to hand it over.

Statement of 2 Jul 2026

Discrepancy between the agreed heat output and the house’s actual requirements

The heat supplier admitted in writing that the contracted output does not match the building’s actual needs and proposed redistribution among metering points.

Statement of 29 Jun 2026
2025 billing

Objections to the service bill for 2025

An overview of the six reservations, including the relevant supporting documents.

01

A delay of 70 days

The 2025 service billing was generated on 9 July 2026. The statutory deadline under § 7 (1) of Act No. 67/2013 expired on 30 April 2026. As late as 15 June 2026 the manager sent advance-payment reminders without mentioning the billing. The reminders dated 15 June 2026 made no mention of the statement of account.

Supporting documents: § 7 (1) and § 13 of Act No. 67/2013; Art. XIII (2) of the statutes.

02

The late-payment penalty should not come from the building’s fund

The delay was caused by the manager, who is also the statutory body. Formally the association owes the penalty, and the manager decides whether to claim it from itself. We would therefore pay the fine out of our own joint funds.

Supporting documents: § 159, § 437 and § 2913 Civil Code (conflict of interest and recourse).

03

Flat owners pay for the electricity used by the commercial car park

In Art. 5.1.2 of the easement agreement of 29 May 2024 the car-park operator undertook to pay its energy and set up its own metering point. Two years later it has none. Car-park technology, lighting and ventilation of the basement run through the building’s meters – and flat owners bear the cost.

Supporting documents: Art. 5.1.2 of the easement agreement; operator’s written confirmation; switchboard diagram RG-CDE-01.

04

Unresolved request for a billing correction

The manager refused a corrected billing citing missing sub-meter readings. The accounting period does not remove the duty to charge owners only their actual costs, and sub-metering is not the only admissible method: consumption can be estimated from installed load and operating profile.

Supporting documents: Act No. 67/2013; manager’s reply citing § 3 (1) of Act No. 563/1991.

05

Easement fee and who bears operating costs

The easement fee is CZK 10,000 + VAT per year for exclusive use of part of the common areas where a third party runs a paid car park. The dispute is not whether it is paid, but how low it is relative to the benefit and who bears energy, cleaning and maintenance the contract expressly assigns to the operator. The 2025 billing shows owners pay them.

Supporting documents: Art. 5.1.1 and 5.1.2 of the easement agreement; 2025 billing.

06

Air-conditioning and heat recovery without prescribed advances

The statutes allow charging these energies to owners of the affected equipment, but assume advances prescribed in advance and billing by actual consumption where measurable. Equal split is only a fallback. Why were no advances prescribed and why equal split when the units have meters?

Supporting documents: Art. XII (3) of the statutes; The administrator’s statement regarding the unauthorised advance payment.

Recommended procedure for checking bills

1Date of issue. It should have arrived by 30 April 2026, by law and by Art. XIII (2) of the statutes.
2Item “Common-area electricity”. You pay a share by flat size. It includes the commercial car park’s consumption.
3Number of persons for your unit. If you did not report it, the statutes set it by layout: 1+kk = 1, 2+kk = 2, 3+kk = 4, 4+kk = 5. Is yours right?
4Air-conditioning and heat recovery. Was an advance ever prescribed for this item, and is it billed by actual consumption or split equally?

Objections must be raised within 30 days of delivery. For the 9 July billing that period has passed for most owners. In that case you file a request for supporting documents and a complaint of incorrectness.

The administrator’s procedure for resolving the issues mentioned

No complaints were lodged regarding the defects mentioned.

We require evidence that the car park operator has fulfilled its contractual obligations regarding operating costs.

We have not been provided with evidence of when and how the administrator verified the establishment of a separate supply point for the car park.

For some of the enquiries, a face-to-face meeting at the shopping centre was offered, but the requested written documentation was not provided.

One company is today the statutory body, the building manager, the purchaser of supplies and the one assessing complaints about its own work.We propose separating the management of the owners’ association from the administration and financial oversight.

Grant a proxy →